March
21, 2008
The Lincoln Electric System Administrative Board held its
regular monthly meeting March 21 at the Lincoln Electric Building. Items from
the meeting, as well as other pertinent information, include...
Capital Improvements through 2014 to Total $257.5 Million
The Lincoln Electric System (LES) Administrative Board approved the $257.5
million Capital Improvement Program (CIP) that is submitted to the City as
part of its budget. Ron Kratzer, Utilities Manager II, said the amount is down
$33 million, or 11.5 percent, from last year’s report.
For 2009-2014, service will be extended to 11,700 new customers, while
increasing service to 3,500 customers. It is projected the number of customers
served by LES will be approximately 140,000. In the next six years, LES will
serve an estimated 84,000 kilowatts of new electric load, which is comparable
to the load of a city the size of Fremont—an annual load growth rate of 1.7
percent.
Projected peak demand will increase from 799 MW in 2008 to 883 MW in 2014, the
CIP report stated.
The following amounts are budgeted in the next six years:
-
$36.8 million on transmission—up about $700,000 from last year’s CIP.
-
$45
million on substations—down $7.9 million.
-
$19.2 million on overhead distribution—down $3.3 million.
-
$83.3 million on underground distribution—down $14.6 million.
-
$988,000 on distribution lines in Waverly—down $19,000.
-
$869,000 on street lights—up $105,000.
-
$71.4 million on Power Supply—down $8.3 million.
New
projects in this year’s CIP report are as follows:
-
115kV line from SW 7th and Saltillo Road and Rokeby.
-
115kV line from Sheldon Station to SW 33rd and Denton Road.
-
Substation at SW 7th and Saltillo Road.
-
Replace a 115-12kV transformer at the 56th and Q substation.
The
CIP will be reviewed with Mayor Chris Beutler next week before it is finalized
and sent to City Planning Dept. on April 7. The Planning Commission will hold
a public hearing on the CIP on May 14.
Integrated Resource Plan Approved by Board
The Lincoln Cooperative Integrated Resource Plan (IRP) that analyzes a variety
of future power supply options for the community was approved Friday (3/21) by
the Lincoln Electric System Administrative Board.
The plan covers LES, the University of Nebraska-Lincoln and other state
agencies (Lincoln Regional Center, Nebraska State Office Building, Nebraska
State Penitentiary), and will be submitted to the U.S. Department of Energy’s
Western Area Power Administration (WAPA) for final approval.
Future power supply options discussed and analyzed in the plan include demand
side, supply side, renewable energy and new power generation options.
LES developed the plan in compliance with federal power purchase contract
provisions. All agencies covered by the plan purchase federal power. WAPA
supplies power to LES from its Upper Missouri Basin hydroelectric plants and
requires its customers to submit an updated IRP every five years. Integrated
resource planning is a process for evaluating the full range of new resource
alternatives available for the purpose of providing adequate and reliable
service to customers.
The community had the opportunity to comment on the plan at two public
meetings hosted by LES, as well as by submitting written comments for the
record.
Other Reports
The following statistics for February were presented to the Board:
|
February 2008 |
February 2007 |
Change |
|
Number of Customers |
|
127,083 |
125,324 |
+1,759 (+1.4%) |
|
Retail Electricity Use (MWh) |
|
259,687 |
247,207 |
+12,480 (+5.0%) |
|
12-Month Average Outage Time/Customer
(minutes) |
|
42.8 |
19.2 |
+23.6 |
Top