LES
Link to LES' video vault Facebook Twitter    Español   Tieng Viêt          Site Map         

Various People

Construction projects
Transmission

Central Lincoln Reliability Project
17th & Holdrege to 21st & N
to 30th & A to 56th & Everett

 

OverviewFAQMaps/PhotosTimelineResourcesAssociated Project Glossary

 

Project update

The Central Lincoln Reliability Project remains on track, with design of the overhead and underground portions completed and construction underway. See the progress map.

Overview

The project’s 115-kilovolt line replaces an underground line installed 36 years ago and will connect four substations: 17th and Holdrege streets, a new substation at 21st and N streets, 30th and A streets, and 56th and Everett streets. (See the map below.)

The new line is necessary to...

  • Replace aging cables.
  • Meet the growing demand for electricity in central Lincoln.
  • Improve system reliability.

Approximately 63 percent of the route will be buried cable, and 37 percent will be overhead power lines. In association with the 115-kV line being placed overhead along South Street, the existing lower-voltage lines will be placed underground. Throughout the project, property owners will be notified in advance of construction. LES expects the Central Lincoln Reliability Project line to be energized in fall 2013.

The transmission line route was approved by the LES Administrative Board in November 2010 after extensive input was gathered via three public open houses, a customer survey, conversations with customers and numerous meetings with public agencies and other stakeholders.

Maps and photo simulations

Place your cursor over the 1, 2 or 3 on the map below, and click on the numbers to get a closer view of the area. When map 1 opens, click on the "View Photo" squares throughout the map to see the existing sites and the future line. Map 2 and 3 show an underground route so there are no photos. (Note: These files are large, so please be patient while waiting for them to open.)

115-kV Transmission Line

For a closer view, click on the 1, 2 and 3 on the map. When map 1 opens, click on the "View Photo" squares throughout the map to see the existing sites and the future line. Map 2 and 3 show an underground route so there are no photos.

Central Lincoln Reliability Project map: 21st & N to 17th & Holdrege Central Lincoln Reliability Project map: 30th & A to 21st & N Central Lincoln Reliability Project map: 56th & Everett to 30th & A Central Lincoln Reliability Project overview map

Top

Timeline

  • 2010 / Route study and selection
  • 2010-2012 / Easement acquisition as required

     Underground - 17th & Holdrege to 32nd & South Street

  • 2012 / Contract awarded to General Cable for the underground duct bank, vaults and cable installation
  • April 2012 / Started construction of underground duct bank and vaults - subcontractor K2 Construction
  • May 2012 / Started bore under Antelope Creek – subcontractor King Contracting, Inc.
  • June 2012 / Completed bore under Antelope Creek
  • Early April 2013 / Cable and accessories delivery
  • Late April 2013 / Start cable installation into duct and vault system – General Cable
  • May 2013 / Planned completion of underground duct bank and vaults
  • Late May 2013 / Complete cable installation into duct and vault system
  • Late May 2013 / Start cable splicing in vaults – General Cable
  • Mid-June 2013 / Start cable terminations or connections at substations – General Cable
  • Late August 2013 / Complete cable terminations or connections at substations
  • Late August 2013 / Complete cable splicing in vaults
  • September 2013 / Inspections, testing, training and demobilization

     Overhead - 32nd & South Street to 56th & Everett

  • July 2012 / – Contract awarded to PAR Electrical Contractors, Inc.
  • September 2012 / Started concrete anchor bolt foundations – subcontractor Longfellow Drilling
  • October 2012 / Started setting poles – PAR Electric Contractors, Inc.
  • Late October 2012 / Released contractor to assist with restoration from damage caused by Hurricane Sandy
  • December 2012 / Contractor returned to continue with pole setting – PAR Electrical Contractors, Inc. and Longfellow Drilling
  • January 2013 / Completed pole installation on South Street
  • February 2013 / Started wire or conductor installation on South Street – PAR Electrical Contractors, Inc.
  • Mid-February 2013 / Completed wire or conductor installation on South Street
  • February 2013 / Completed the setting of poles on 56th Street and Longfellow Drilling demobilized
  • March 2013 / Completed wire or conductor installation on 56th Street, and PAR Electrical Contractors, Inc. demobilized
  • March and April 2013 / Restoration of sidewalks and yards on both South Street and 56th Street

Top

For more information

Top

5/9/13