Construction & Contractors

Building a better community

Our customers depend on us to power their homes, so we’re committed to continuously improve service and reliability across the service territory. We continue to maintain our outstanding service reliability of 99.99%. To maintain the excellent service our customers expect, we acknowledge the need to repair, replace, build, upgrade and extend the electric system. Below, see details about LES' major construction projects in the works. 

(Are you a building contractor? Click here for info on how we can work together to better anticipate equipment needs in your building projects during this time of supply chain issues.)

Major Projects
Denton Road: Oversized Load Project

Planned Power Outage

Thursday, June 18, 2026: 8 a.m.-2 p.m.

Status: On Schedule

LES will be moving power lines to allow a private contractor to safely move an oversized load in southwest Lincoln. Area impacts homes around W. Denton Road and S. Coddington Avenue. Exact area is provided in the map below.

Area impacted map

Please prepare for a planned power outage on June 18, beginning at 8 a.m. that may last until 2 p.m. Once the load has safely passed, LES crews will return the power lines to service and restore power to your home or business as quickly as possible.

NOTE: This move requires the coordination of several utilities, state and local agencies, regional transmission authorities and more. Weather or other factors may impact the date and time of this outage. Updates will be made to this page in case of schedule changes.

Padmounted Equipment Inspection Program

Padmounted Equipment Inspection Program Map

Some equipment is inspected on a more frequent basis and may not be reflected in the shaded portion of the map displayed above.

The Underground Distribution Asset Management (UDAM) program inspects and performs maintenance on LES padmounted electrical equipment throughout the service territory on a 5 year cycle. This inspection evaluates equipment conditions and determines where targeted construction may be needed to maintain high system reliability. The 2026 inspection will begin in March and work is expected to be complete by the end of 2026. Inspections will be performed by LES crews, as well as crews from our contractor, Kidwell.

Saltillo Relocation Project

SALTILLO RELOCATION PROJECT MAP

In preparation for the Lancaster County Roundabout and Resurfacing Project along Saltillo Road, LES will move existing overhead lines that are in conflict with the roadway project and will install underground cables and at-grade equipment within the project area.

This project will improve the reliability and safety for our customers while improving the aesthetics along Saltillo Road.

Overhead Distribution Asset Management Project

ODAM BGI 10-Year Cycle map

ODAM AGI Attachment A 5-Year Cycle Map

The Overhead Distribution Asset Management (ODAM) program improves reliability and safety of the LES electrical system through inspections of our infrastructure. This proactive maintenance results in timely resolution of potential issues. 

The ODAM program identifies and addresses any issues before they lead to outages or safety hazards. The program includes two main inspection components: the Above Grade Inspection (AGI) and the Below Grade Inspection (BGI), each following specific cycles to ensure comprehensive coverage across our service area. 

Detailed Inspection Cycle 

Above Grade Inspection (AGI):

  • Cycle: Every 5 years
     
  • Scope: The AGI inspects LES’ overhead equipment attached to wood poles from ground level to pole top. This inspection cycle covers one area in north Lincoln and one in south Lincoln each year, ensuring that all areas within the service territory are thoroughly inspected over a five-year period. We focus on identifying issues such as structural integrity, electrical safety and environmental hazards.

Below Grade Inspection (BGI):

  • Cycle: Every 10 years
     
  • Scope: The BGI addresses the condition of the wood poles below ground level. This inspection involves a thorough examination of the poles’ health and includes remedial treatment of the poles to extend their service life and ensure continued safety and reliability.

Coordinated Inspections and Prioritization

The AGI and BGI are designed to work in tandem, with overlapping inspections in certain areas to ensure both above and below ground issues are addressed comprehensively. Work is then prioritized based on the severity of any issues found:

  • Priority 1 (Immediate): Issues posing imminent safety or environmental hazards or those likely to cause an outage are addressed within 1-7 days.
     
  • Priority 3 (Medium): Deficiencies that present potential safety or outage concerns but are not immediate are resolved within 30 days.
     
  • Priority 5 (Routine): Issues that do not pose immediate risks are scheduled for resolution within the regular maintenance cycle, typically within three years. 
UNL Services Project

UNL Services Project Map

Project start: January 2026

Project completion: Fall 2026

Project Area: UNL Campus, North Bottoms

LES crews and contractors will work along the north side of UNL campus. This project will increase the electrical capacity of the area by converting overhead lines to underground; this will maintain the reliability of the transmission system. 

Project Impact: There is a potential for lane closures, sidewalk closures and metered parking closures. The Billy Wolff Trail and Salt Creed Rd will be impacted at certain times during this project.

SW 27th, A-O Street Feeder Project

SW 27th, A-O Street Feeder Project Map

Project start: Spring 2026

Project completion: Fall 2026

LES and contractors will add another feeder circuit to support load growth in the area and support the potential for additional growth. There will be minimal traffic impacts during this project. 

Construction planning process

01 - Model the electric grid

Annually, the LES System Planning Department models the LES electric grid to simulate real-world situations to ultimately develop a construction work plan. The model identifies areas of weakness, overloads and overall grid stress points. Out of the annual studies, specific projects are developed to remedy deficiencies, issues and problem areas. Other projects are identified when individual feeder circuits perform in a substandard manner, or future growth requires expanding the circuits. All these potential projects are prioritized to bring the most value to the organization.

02 - Engineer design package development

Following identification, the LES Design Engineering team takes conceptual ideas and converts them to an engineering design package that can be used to construct the project and that meets the National Electrical Safety Code provisions. Ensuring the safety of the public and the LES team is vital to the success of any construction project. When placing the LES electrical facilities on customer properties, LES Engineering and Land Management work with the customer-owner to find the right location for cable, pole, transformer or switch.

03 - Construction starts

LES Transmission & Distribution Construction puts into action the organization's priorities to get the new or replacement facilities into service. Many LES employees are involved in the projects. LES also utilizes external consultants and contractors to supplement projects when specialized equipment is required, or internal resources are not available by the required in-service date.

Hard hat & blueprints

Construction projects map

This map illustrates current LES construction projects within the service area. To view details about a project, click the colored area, and a pop-up containing additional information such as a description, bounds, start and end dates will display. If a contractor is assisting LES, the contractor logo(s) will appear at the bottom of the pop-up window. If you have questions about a construction project, contact LES by calling 402.475.4211.

If you see a construction flag in your yard but don't see a project in your area on the LES map, it may be a city of Lincoln project